Project Update: May 31st

Terminal Projects

  • Installation of the wood ceiling and stone walls in the Checkpoint and Holdroom area is in progress.
  • Drywall is completed and painting has begun in the Checkpoint and Holdroom areas.
  • Excavation and shoring is nearly completed for the restaurant project, with the footings and foundation up next.

 

Runway Project

  • We are at Day 51 of the 78 Day Runway Project.
  • Aggregate base course has been completely installed.
  • Paving has started on the southern end of the runway.
  • Installation of the runway lights has begun.
  • Grading outside of the runway shoulders has started.

 

 

  • Testing of soil compaction.