Project Update: May 31st
Terminal Projects
- Installation of the wood ceiling and stone walls in the Checkpoint and Holdroom area is in progress.
- Drywall is completed and painting has begun in the Checkpoint and Holdroom areas.
- Excavation and shoring is nearly completed for the restaurant project, with the footings and foundation up next.
Runway Project
- We are at Day 51 of the 78 Day Runway Project.
- Aggregate base course has been completely installed.
- Paving has started on the southern end of the runway.
- Installation of the runway lights has begun.
- Grading outside of the runway shoulders has started.