Construction Projects
JAC Projects Overview
The Jackson Hole Airport has had several large capital projects taking place starting the spring of 2021 through the winter of 2022. These projects will allow JAC to operate safely and support airline operations while enhancing the traveler experience. Safety, efficiency, and being good stewards to the environment are our top priority every day, and these commitments are considered with every project plan developed for JAC.
Project | Status | Timeline |
---|---|---|
Restaurant & Gate Project | Complete | Completed December 2022 |
Runway Reconstruction - Phase 3 | Complete | Completed September 2022 |
TSA Checkpoint Project | Complete | Completed June 2022 |
Runway Reconstruction - Phase 2 | Complete | Completed June 2022 |
Runway Reconstruction - Phase 1 | Complete | Completed October 2021 |
Baggage Claim Marketplace | Complete | Completed November 2021 |
Entrance Vestibule & Backflow | Complete | Completed May 2021 |
Ticketing Counter Project | Complete | Completed May 2021 |
Past Capital Projects
Past Capital Projects
Start Date: May 2021End Date: December 2022
The Jackson Hole Airport is our community’s airport, and these terminal projects will help JAC accommodate demands placed on the facility. Many of the projects outlined below increase available space to safely and efficiently conduct airport operations while continuing to meet travelers’ high expectations for customer service and experience.
View ProgressRelated News
JAC Construction Update: Vlog Episode 7
Jackson Hole Airport’s final vlog in their Construction Update Series featuring the new restaurant and gate area. These projects complete a comprehensive Capital Projects Plan the Airport began in the spring of 2022.
Phase 3 of the Runway Project Scheduled August 8th – September 8th, 2022
The Jackson Hole Airport will begin the final phase (known as Phase 3) of the Runway 1/19 Reconstruction project nightly on August 8th through September 8th. The primary work to be completed in Phase 3 includes grooving and permanent runway striping. Grooving of the runway is an essential safety measure required by the FAA as […]
JAC Construction Update Vlog: Episode 6
Isaac is joined by Dustin Havel, Assistant Airport Director – Operations, to highlight some of the project updates in the parking, restaurant and runway areas of the Airport.
We Want to hear from you!
We are accepting feedback submission. Submit your thoughts today.
Submit FeedbackStay Up to Date
Sign-up here for emails about construction schedules and progress
For questions or concerns about construction project at JAC, please email community@jhairport.org