Project Update: April 22nd

  • Construction is happening 24/7 (day and night, rain or shine).
  • Materials from the restaurant and security checkpoint projects are being incorporated into the runway project negating the need to truck offsite.
  • The hold room and security checkpoint area roof is nearly complete; all the steel has been installed and they will be pouring the first section of the concrete slab shorty.
  • Runway milling schedule is now 12 hours per day.

 

 

  • Milling operation on the west shoulder of the runway.