Terminal Projects
Terminal Improvement Timeline
Phase | Description | Timeline |
---|---|---|
TSA Checkpoint Project | Redesigning the security screening and holding areas to raise the functionality and safety. | January 3, 2022 - June 27, 2022 |
Restaurant Project | Renovating the restaurant area to increase customer service and comfortability. | April 2022 - November 2022 |
Gate Project | Additional boarding gates to raise operational efficiency. | April 2022 - November 2022 |
Baggage Claim Marketplace | Complete | |
Entrance Vestibule & Backflow | Complete | |
Ticketing Counter Project | Complete |
TSA CHECKPOINT PROJECT
The Security Screening Checkpoint is the oldest part of the terminal building at JAC. To accommodate modern security screening technology needs, the Checkpoint area will be undergoing a complete redesign.
The hold room (area where passengers wait to board planes) adjacent to the checkpoint will also be renovated to create additional seating and flexible free-standing space.
The Checkpoint project will begin on January 3rd of 2022 and is expected to be completed by June 27 of 2022, to coincide with the runway re-opening. From January of 2022 through April of 2022, travelers will be using a temporary Security Checkpoint equipped with three screening lanes, until the runway closure begins. Upon completion, travelers can expect to experience a safer Checkpoint with four active screening lanes.
Restaurant Project
The restaurant area project at JAC will allow for additional space and updated seating and service areas. A full basement will be constructed under the new restaurant to allow for additional storage. The new design has taken into consideration the flow of foot traffic, ease of access, and efficiency.
Restaurant construction will begin in April of 2022 and is expected to be completed by the end of November of 2022. Interim food and beverage options will be available in a limited capacity, post-security, throughout the duration of this project.
Gate Project
The gate area adjacent to the restaurant will refurbished, adding additional boarding gates. Common use technology will be installed at the gates to allow for flexibility with space and airline operations. The pet relief area and mothers’ room will be relocated and will remain in-service throughout the duration of the construction of the new restaurant and gate area.
BAGGAGE CLAIM MARKETPLACE
This project was completed in November, 2021.
In order to meet the needs of the public and travelers, the airport has constructed a new Marketplace in the baggage claim building. This marketplace provides additional seating areas, a variety of options for food, drink, and other essentials to airport users.
ENTRANCE VESTIBULE & BACKFLOW
This project has been completed.
TICKETING COUNTER PROJECT
This project has been completed.
We Want to hear from you!
We are accepting feedback submission. Submit your thoughts today.
Submit FeedbackStay Up to Date
Sign-up here for emails about construction schedules and progress
For questions or concerns about construction project at JAC, please email community@jhairport.org