Runway Reconstruction Closure: April 11, 2022-June 28, 2022

TSA Checkpoint Remodel

Project Overview

The Security Screening Checkpoint is the oldest part of the terminal building at JAC. To accommodate new security screening technology, the Checkpoint will be undergoing a complete remodel and expansion.

The holdroom (area where passengers wait to board planes) adjacent to the checkpoint will also be expanded by 1,000 square feet to create additional seating and flexible free-standing space.

The Checkpoint project will begin in on January 19th of 2022 and is expected to be completed by June 27 of 2022, to coincide with the runway re-opening. From January of 2022 through April of 2022, travelers will be using a temporary Security Checkpoint equipped with three screening lanes, until the runway closure begins. Upon completion, travelers can expect to experience a spacious Checkpoint with four active screening lanes.

TSA Checkpoint Remodel Timeline

ProjectDescriptionCompletion Date
Start DateJanuary 19, 2022
Completion DateCoincides with Runway ReopeningJune 27, 2022

FAQ's

The Security Screening Checkpoint is the oldest section of the terminal building at JAC and is due for upgrades.

We always encourage folks traveling to arrive two hours early to JAC from the time of their departure. During construction, arriving at least two hours early will be essential to ensuring that you are able to go through ticketing and security before your boarding time arrives.

The dates for the Security Screening Checkpoint construction are January 19 – June 2022. From January – April 2022, travelers will need to allow for extra time to get through security.

Yes, those that qualify for TSA Precheck will continue to receive this
service.

More Projects

Runway Reconstruction

Start Date: July 6, 2021
End Date: September 2022

Jac’s runway is in need a full reconstruction. The last time the runway was fully reconstructed was in the 1970’s. The asphalt runway at JAC has been rehabbed four times since it was originally constructed in the late1970’s and it is due for a total reconstruction in the spring of 2022 which will include a 78-day runway closure.

View Progress

Ticketing Counter Expansion

Completion Date: May 2021
Learn More

Stay Connected

We Want to hear from you!

We are accepting feedback submission. Submit your thoughts today.
Submit Feedback

Stay Up to Date

Sign-up here for emails about construction schedules and progress

For questions or concerns about construction project at JAC, please email community@jhairport.org

Check your Flight Status

Use the toggle below to switch between Arrival and Departure Status

Reduce the impact of your flight with carbon offsets.

Summer Schedule

Current Conditions

Reduce the impact of your flight with carbon offsets.

33°F / 1°C

High 43°F / 6°C Low 26°F / -3°C

Current Skies: Clear
Current Visibility: 10 miles
Wind: 9 mph out of the South-Southwest

  • Sunday

    52°F / 11°C

    SSE 3 mph
  • Monday

    64°F / 18°C

    SSE 5 mph
  • Tuesday

    58°F / 14°C

    SE 5 mph
Full Forecast