Construction Projects

JAC Projects Overview

The Runway at JAC is open!

The Jackson Hole Airport will have several large capital projects taking place during the spring of 2021 through the summer of 2022. These projects will allow JAC to operate safely and support airline operations while enhancing the traveler experience. Safety, efficiency, and being good stewards to the environment are our top priority every day and these commitments are considered with every project plan developed for JAC.

ProjectStatusTimeline
Runway Reconstruction - Phase 3ScheduledJuly - September, 2022
Restaurant & Gate ProjectScheduledApril 11 - November, 2022
TSA Checkpoint ProjectCompleteCompleted June 2022
Runway Reconstruction - Phase 2 - Runway ClosedCompleteCompleted June 2022
Entrance Vestibule & BackflowCompleteCompleted May 2021
Ticketing Counter ProjectCompleteCompleted May 2021
Baggage Claim MarketplaceCompleteCompleted May 2021
Runway Reconstruction - Phase 1CompleteCompleted October 2021

Runway Reconstruction Project

Runway Reconstruction – Phase 2 Completed – Phase 3

Start Date: July 6, 2021
End Date: September 2022

JAC’s runway is in need of a full reconstruction. The last time the runway was fully reconstructed was in the 1970’s. The asphalt runway at JAC has been rehabbed four times since it was originally constructed in the late 1970’s and it is due for a total reconstruction in the spring of 2022 which will include a 78-day runway closure. The 78-day closure associated with Phase 2 has been completed. Phase 3 will be underway August 8th - September 8th, 2022.

View Progress

Terminal Projects

Terminal Projects

Start Date: May 2021
End Date: November 2022

The Jackson Hole Airport is our community’s airport, and these terminal projects will help JAC accommodate demands placed on the facility. Many of the projects outlined below increase available space to safely and efficiently conduct airport operations while continuing to meet travelers’ high expectations for customer service and experience.

View Progress

Projects Progress

Completion Progress: 100%

Virtual Tour

Related News

Additional Resources

Stay Connected

We Want to hear from you!

We are accepting feedback submission. Submit your thoughts today.
Submit Feedback

Stay Up to Date

Sign-up here for emails about construction schedules and progress

For questions or concerns about construction project at JAC, please email community@jhairport.org

Check your Flight Status

Use the toggle below to switch between Arrival and Departure Status

Reduce the impact of your flight with carbon offsets.

Summer Schedule Winter Schedule

Current Conditions

Reduce the impact of your flight with carbon offsets.

74°F / 23°C

High 81°F / 27°C Low 44°F / 7°C

Current Skies: Clear
Current Visibility: 10 miles
Wind: 7 mph out of the West

  • Wednesday

    90°F / 32°C

    E 3 mph
  • Thursday

    93°F / 34°C

    SSE 5 mph
  • Friday

    86°F / 30°C

    SSW 3 mph
Full Forecast